Build your timeline
Start with a template, then adjust each leg to match your carrier's schedule and your own experience of the lane.
Your timeline
What a door-to-door timeline actually contains
The single most common planning mistake is treating the carrier's published port-to-port figure as the delivery date. On a typical ocean import into Pakistan, the vessel leg is often less than half the total elapsed time.
| Stage | What happens | Counted in |
|---|---|---|
| Cargo ready to pickup | Booking confirmed, transport arranged, cargo collected from the supplier | Working days |
| Export haulage | Inland move from factory to port or airport, plus any queueing at the terminal gate | Working days |
| Export customs and cut-off | Documentation, export declaration, and waiting for the vessel or flight cut-off | Working days |
| Main carriage | The vessel or aircraft movement itself, including any transhipment call | Calendar days |
| Discharge and destination handling | Unloading, terminal transfer, container destuffing for LCL | Calendar days |
| Import customs clearance | Declaration, assessment, duty payment, examination if selected | Working days |
| Delivery | Port release, inland haulage, unloading at the consignee | Working days |
LCL adds three to seven days over FCL at each end because the container has to be stuffed at origin and destuffed at destination alongside other shippers' cargo, and neither happens until the consolidator has a full box.
Why schedules slip
Published transit times describe the intended service, not the observed one. The most frequent causes of delay, in roughly the order we see them:
- Rolled cargo. The booking is confirmed but the container does not make the intended sailing because the vessel is overbooked. On tight capacity this can repeat.
- Transhipment. Any routing that changes vessel adds a connection risk. A missed connection at a hub typically costs one full weekly rotation.
- Customs examination. Selection for scanning or physical examination is usually a matter of days, but documentary discrepancies can extend it considerably.
- Port congestion and weather. Berth waiting, monsoon closures and fog disruption at either end.
- Documentation. A missing certificate of origin or an incorrect HS code stops the clearance regardless of where the cargo is.
- Holiday periods. Chinese New Year, Eid, Golden Week and the Christmas period each compress capacity for weeks either side.
This is why the calculator includes a buffer field. Quote the buffered date to your customer and the unbuffered one to nobody.